Regent Aarya, Vile Parle East
by Regent Sparsh · Vile Parle East, Mumbai 400057 · Map
- Launched
- Mar 20263 yrs promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 28%Mid-construction
- Booked (free sale)
- 0 of 110%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 11 units
Land-owner share1 unit, not for sale
Total 12 units. Land-owner units are not for sale.
Project facts
- 2 BHK
- 1
- 3 BHK
- 10
- 4 BHK
- 1
- Total units
- 12
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Land-owner share (not for sale)
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 28% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 2 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2029 | Jan 2028 |
| Concrete structure (RCC) | 28% | 0% |
| Units booked (free sale) | 0% | 8% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- New Manibhuvan, Vile Parle East
- Arham Heritage, Vile Parle East
- Poddar Vasundhara, Vile Parle East
- Silver Arch, Vile Parle East
- The Windsor - Mantri Smruti, Vile Parle East
- Alliance Tanvi, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| New Manibhuvan | March 2026 | December 2026 | 70% | 1 unit booked out of 14 units for sale |
| Arham Heritage | April 2026 | January 2029 | 0% | 0 units booked out of 20 units for sale |
| Poddar Vasundhara | February 2026 | December 2027 | 42% | 1 unit booked out of 12 units for sale |
| Silver Arch | January 2026 | March 2028 | 0% | 1 unit booked out of 5 units for sale |
| The Windsor - Mantri Smruti | January 2026 | December 2027 | 0% | 6 units booked out of 12 units for sale |
| Alliance Tanvi | December 2025 | December 2028 | 0% | No units for sale: rehab units only |
About this project
Regent Aarya by Regent Sparsh is a 12-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in March 2026 with possession due in March 2029. 0 units booked out of 11 units for sale. The concrete structure (RCC) is 28% complete.
Read full summary
Regent Aarya is a BMC-sanctioned project by Regent Sparsh in Vile Parle East, Mumbai 400057, registered with MahaRERA as PR1180002502662. It was launched in March 2026. It has 12 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 12 units, 11 are for sale and 1 is the land-owner's share, not for sale.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 28% complete, final finishes not started.
0 units booked out of 11 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 28%.