Modirealty Rudraksh, Kandivali West

by Modirealty Developers Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Jan 20264 yrs 8 mths promised
Possession (MahaRERA)
Sep 2030Not extended
Concrete structure
5%Mid-construction
Booked (free sale)
0 of 300% · 17 rehab units
Buildings
11 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 30 units

Rehab17 units for existing members

Total 47 units. Rehab units are not for sale.

Project facts

2 BHK
20
3 BHK
20
Other units
7
Total units
47
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
0
Free-sale units
30
Rehab units
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)5%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 80%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 5%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 5%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%5%0%0
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 20–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 8 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Sep 2030Jun 2029
Concrete structure (RCC)5%14%
Units booked (free sale)0%25%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Modirealty Rudraksh by Modirealty Developers Private Limited is a 47-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in January 2026 with possession due in September 2030. 0 units booked out of 30 units for sale. The concrete structure (RCC) is 5% complete.

Read full summary

Modirealty Rudraksh is a BMC-sanctioned project by Modirealty Developers Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as PM1180002502054. It was launched in January 2026. It has 47 units in 1 building: 40 homes (2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 30 are for sale and 17 are rehab units for existing members.

Its registered possession date is September 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.

0 units booked out of 30 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 5%.