Skip to main content

Modern Roop-Kamal Co-Operative Housing Society Ltd, Kandivali West

by Konark Structural Engineers Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Oct 20254 yrs 2 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
48%Mid-construction
Booked (free sale)
0 of 280% · 38 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 28 units

Rehab38 units for existing members

Total 66 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
48
3 BHK
10
Other units
2
Total units
66
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
38

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)48%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 50%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 48%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 48%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%48%0%0
100%0%0%0
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400067

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths4 yrs 6 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2029Mar 2030
Concrete structure (RCC)48%10%
Units booked (free sale)0%42%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Modern Roop-Kamal Co-Operative Housing Society Ltd by Konark Structural Engineers Private Limited is a 66-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2025 with possession due in December 2029. 0 units booked out of 28 units for sale. The concrete structure (RCC) is 48% complete.

Read full summary

Modern Roop-Kamal Co-Operative Housing Society Ltd is a BMC-sanctioned project by Konark Structural Engineers Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as PR1180002501123. It was launched in October 2025. It has 66 units in 1 building: 64 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 66 units, 28 are for sale and 38 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 48% complete, final finishes not started.

0 units booked out of 28 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 48%.