Goyal Meridian, Borivali West

by Goyal Realty Ventures Private Limited · Borivali West, Mumbai 400091 · Map

Launched
Feb 20263 yrs 8 mths promised
Possession (MahaRERA)
Oct 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
5 of 4711% · 44 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 47 units

Rehab44 units for existing members

Total 91 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
4
3 BHK
76
Other units
7
Total units
91
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
47
Rehab units
44

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 90%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%5
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400091

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400091
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 8 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Oct 2029Feb 2030
Concrete structure (RCC)0%0%
Units booked (free sale)11%9%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Goyal Meridian by Goyal Realty Ventures Private Limited is a 91-unit MHADA-sanctioned project in Borivali West, Mumbai 400091, launched in February 2026 with possession due in October 2029. 5 units booked out of 47 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Goyal Meridian is a MHADA-sanctioned project by Goyal Realty Ventures Private Limited in Borivali West, Mumbai 400091, registered with MahaRERA as PM1180002502363. It was launched in February 2026. It has 91 units in 1 building: 84 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 91 units, 47 are for sale and 44 are rehab units for existing members.

Its registered possession date is October 2029, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

5 units booked out of 47 units for sale (11%). Since the July 2026 update, 5 more units have been booked.