Gorai Samadhan Cooperative Housing Society Limited, Borivali West

by Gorai Samadhan Cooperative Housing Society Limited · Borivali West, Mumbai 400091 · Map

Launched
Dec 20251 yr 6 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
30%Mid-construction
Booked (free sale)
28 of 28100% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale28 booked out of 28 units

Rehab16 units for existing members

Total 44 units. Rehab units are not for sale.

Project facts

2 BHK
15
3 BHK
29
Total units
44
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
28
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)30%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 30%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 30%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%30%0%28
100%10%0%28
0%0%0%28

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400091

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400091
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 6 mths3 yrs
Possession date extendedNo1 of 6
Possession date (MahaRERA)Jun 2027Jul 2029
Concrete structure (RCC)30%16%
Units booked (free sale)100%11%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Gorai Samadhan Cooperative Housing Society Limited by Gorai Samadhan Cooperative Housing Society Limited is a 44-unit MHADA-sanctioned project in Borivali West, Mumbai 400091, launched in December 2025 with possession due in June 2027. 28 units booked out of 28 units for sale. The concrete structure (RCC) is 30% complete.

Read full summary

Gorai Samadhan Cooperative Housing Society Limited is a MHADA-sanctioned project by Gorai Samadhan Cooperative Housing Society Limited in Borivali West, Mumbai 400091, registered with MahaRERA as PR1180002501714. It was launched in December 2025. It has 44 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 28 are for sale and 16 are rehab units for existing members.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.

28 units booked out of 28 units for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 10% to 30%.