Jalkirti CHS Ltd Redevelopment Project, Borivali West

by Balajee Homes And Realtors LLP · Borivali West, Mumbai 400091 · Map

Launched
Dec 20254 yrs promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
4 of 3910% · 73 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 39 units

Rehab73 units for existing members

Total 112 units. Rehab units are not for sale.

Project facts

1 BHK
23
2 BHK
61
Other units
28
Total units
112
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
39
Rehab units
73

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation85%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 85%Oct 2026: Excavation 85%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 85%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
85%0%0%4
85%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400091

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400091
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs3 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Jul 2029
Concrete structure (RCC)0%4%
Units booked (free sale)10%21%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Jalkirti CHS Ltd Redevelopment Project by Balajee Homes And Realtors LLP is a 112-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in December 2025 with possession due in December 2029. 4 units booked out of 39 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Jalkirti CHS Ltd Redevelopment Project is a BMC-sanctioned project by Balajee Homes And Realtors LLP in Borivali West, Mumbai 400091, registered with MahaRERA as PR1180002501814. It was launched in December 2025. It has 112 units in 2 buildings: 84 homes (1 and 2 BHK) and 28 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 112 units, 39 are for sale and 73 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 85% complete, structure (RCC) not started, final finishes not started.

4 units booked out of 39 units for sale (10%). Since the July 2026 update, 4 more units have been booked.