Brahmand Galaxy, Borivali West

by Devki Enterprise · Borivali West, Mumbai 400092 · Map

Launched
Mar 20266 yrs 9 mths promised
Possession (MahaRERA)
Dec 2032Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 140% · 104 rehab units
Buildings
31.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 14 units

Rehab104 units for existing members

Total 118 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
71
3 BHK
21
4 BHK
1
5+ BHK
1
Other units
18
Total units
118
Buildings
3
Land
1.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
104

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation92%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 92%Oct 2026: Excavation 92%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 92%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
92%0%0%0
92%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 50–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 9 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2032Nov 2029
Concrete structure (RCC)0%0%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Brahmand Galaxy by Devki Enterprise is a 118-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in March 2026 with possession due in December 2032. 0 units booked out of 14 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Brahmand Galaxy is a BMC-sanctioned project by Devki Enterprise in Borivali West, Mumbai 400092, registered with MahaRERA as PM1180002502775. It was launched in March 2026. It has 118 units in 3 buildings: 100 homes (1, 2, 3, 4 and 5+ BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 118 units, 14 are for sale and 104 are rehab units for existing members.

Its registered possession date is December 2032, unchanged since launch. Construction: excavation 92% complete, structure (RCC) not started, final finishes not started.

0 units booked out of 14 units for sale (0%).