Ipsit Deep Darshan, Borivali West

by Ipsit Incline · Borivali West, Mumbai 400092 · Map

Launched
May 20263 yrs 7 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
8 of 909% · 50 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 90 units

Rehab50 units for existing members

Total 140 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
12
2 BHK
75
3 BHK
25
Other units
27
Total units
140
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
90
Rehab units
50

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 50%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%8
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths4 yrs
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2029May 2030
Concrete structure (RCC)0%0%
Units booked (free sale)9%0%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ipsit Deep Darshan by Ipsit Incline is a 140-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in May 2026 with possession due in December 2029. 8 units booked out of 90 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Ipsit Deep Darshan is an SRA-sanctioned project by Ipsit Incline in Borivali West, Mumbai 400092, registered with MahaRERA as PM1180002600345. It was launched in May 2026. It has 140 units in 2 buildings: 113 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 27 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 140 units, 90 are for sale and 50 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

8 units booked out of 90 units for sale (9%). Since the July 2026 update, 8 more units have been booked.