Devendra Chsl, Borivali West

by Amar Associates · Borivali West, Mumbai 400092 · Map

Launched
Apr 20261 yr 11 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
98%Mid-construction
Booked (free sale)
0 of 570% · 75 rehab units
Buildings
22 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 57 units

Rehab75 units for existing members

Total 132 units. Rehab units are not for sale.

Project facts

1 BHK
12
2 BHK
72
3 BHK
35
Other units
13
Total units
132
Buildings
2
Land
2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
57
Rehab units
75

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 98%Oct 2026: Concrete structure (RCC) 98%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 98%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%0%0
100%98%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 11 mths4 yrs 1 mth
Possession date extendedNo1 of 6
Possession date (MahaRERA)Mar 2028Jun 2030
Concrete structure (RCC)98%0%
Units booked (free sale)0%2%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Devendra Chsl by Amar Associates is a 132-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in April 2026 with possession due in March 2028. 0 units booked out of 57 units for sale. The concrete structure (RCC) is 98% complete.

Read full summary

Devendra Chsl is a BMC-sanctioned project by Amar Associates in Borivali West, Mumbai 400092, registered with MahaRERA as PR1180002600178. It was launched in April 2026. It has 132 units in 2 buildings: 119 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 132 units, 57 are for sale and 75 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 98% complete, final finishes not started.

0 units booked out of 57 units for sale (0%).