Jade, Bandra West
by Sosar Infinity LLP · Bandra West, Mumbai 400050 · Map
- Launched
- Mar 20263 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 9%Mid-construction
- Booked (free sale)
- 1 of 333% · 14 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 3 units
Rehab14 units for existing members
Total 17 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 6
- 3 BHK
- 7
- Other units
- 4
- Total units
- 17
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 3
- Rehab units
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 9% | 0% | 1 | |
| 20% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400050
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 4 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Dec 2029 |
| Concrete structure (RCC) | 9% | 0% |
| Units booked (free sale) | 33% | 18% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Kripa Aqua, Bandra West
- Ekta Victoria, Bandra West
- Le Repos, Bandra West
- Mansion Xxi, Bandra West
- 9B Luxe Residences By Vraj Krupa Group, Bandra West
- Omnia Residences, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kripa Aqua | March 2026 | December 2028 | 20% | 6 units booked out of total 14 units |
| Ekta Victoria | February 2026 | December 2028 | 0% | 4 units booked out of 6 units for sale |
| Le Repos | February 2026 | December 2030 | 0% | 0 units booked out of 5 units for sale |
| Mansion Xxi | May 2026 | December 2032 | 0% | 0 units booked out of 37 units for sale |
| 9B Luxe Residences By Vraj Krupa Group | June 2026 | December 2031 | 0% | 1 unit booked out of 4 units for sale |
| Omnia Residences | October 2025 | December 2028 | 0% | 1 unit booked out of total 9 units |
About this project
Jade by Sosar Infinity LLP is a 17-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in March 2026 with possession due in December 2029. 1 unit booked out of 3 units for sale. The concrete structure (RCC) is 9% complete.
Read full summary
Jade is a BMC-sanctioned project by Sosar Infinity LLP in Bandra West, Mumbai 400050, registered with MahaRERA as PM1180002502855. It was launched in March 2026. It has 17 units in 1 building: 13 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 17 units, 3 are for sale and 14 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 9% complete, final finishes not started.
1 unit booked out of 3 units for sale (33%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 0% to 9%.