Kripa Aqua, Bandra West

by Kripa Oneness Private Limited · Bandra West, Mumbai 400050 · Map

Launched
Mar 20262 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
20%Mid-construction
Booked
6 of 1443%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
4
1 BHK
2
2 BHK
7
3 BHK
1
Total units
14
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Reserved units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)20%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 20%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 20%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%6
100%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400050

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths4 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Jun 2030
Concrete structure (RCC)20%0%
Units booked43%18%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Kripa Aqua by Kripa Oneness Private Limited is a 14-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in March 2026 with possession due in December 2028. 6 units booked out of total 14 units. The concrete structure (RCC) is 20% complete.

Read full summary

Kripa Aqua is a BMC-sanctioned project by Kripa Oneness Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002502548. It was launched in March 2026. It has 14 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.

6 units booked out of total 14 units (43%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 20%.