Ekta Victoria, Bandra West
by Ekta Housing Private Limited · Bandra West, Mumbai 400050 · Map
- Launched
- Feb 20262 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 4 of 667% · 11 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 6 units
Rehab11 units for existing members
Total 17 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 2 BHK
- 10
- 3 BHK
- 5
- 5+ BHK
- 1
- Total units
- 17
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 4 | |
| 30% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400050
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Dec 2029 |
| Concrete structure (RCC) | 0% | 4% |
| Units booked (free sale) | 67% | 17% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Le Repos, Bandra West
- Kripa Aqua, Bandra West
- Jade, Bandra West
- Zahra, Bandra West
- Paradigm Green Acrres, Bandra West
- Mansion Xxi, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Le Repos | February 2026 | December 2030 | 0% | 0 units booked out of 5 units for sale |
| Kripa Aqua | March 2026 | December 2028 | 20% | 6 units booked out of total 14 units |
| Jade | March 2026 | December 2029 | 9% | 1 unit booked out of 3 units for sale |
| Zahra | December 2025 | December 2028 | 29% | 15 units booked out of 21 units for sale |
| Paradigm Green Acrres | April 2026 | December 2029 | 0% | 0 units booked out of 11 units for sale |
| Mansion Xxi | May 2026 | December 2032 | 0% | 0 units booked out of 37 units for sale |
About this project
Ekta Victoria by Ekta Housing Private Limited is a 17-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in February 2026 with possession due in December 2028. 4 units booked out of 6 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Ekta Victoria is a BMC-sanctioned project by Ekta Housing Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002502359. It was launched in February 2026. It has 17 units in 1 building, with 1 RK, 2 BHK, 3 BHK and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 17 units, 6 are for sale and 11 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
4 units booked out of 6 units for sale (67%). Since the July 2026 update, 3 more units have been booked.
Ekta's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 8 |
|---|---|
| Total units across these projects | 831 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 3 |
| Lapsed | 0 |
| Under construction | 2 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Ekta projects | 85 (4 of 8 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.