Rustomjee Ozone Skye, Malad West
by Keystone Realtors Limited · Malad West, Mumbai 400064 · Map
- Launched
- Jul 20265 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2032Extended by 4 mths
- Concrete structure
- 0%Early stage
- Booked
- 0 of 1280%
- Buildings
- 12 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 12
- 2 BHK
- 55
- 3 BHK
- 61
- Total units
- 128
- Buildings
- 1
- Land
- 2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400064
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 5 mths | 4 yrs 5 mths |
| Possession date extended | By 4 mths | 0 of 5 |
| Possession date (MahaRERA) | Apr 2032 | Mar 2031 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked | 0% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Rashmi Icon, Malad West
- Brahmand, Malad West
- Ambit Iconia, Malad West
- Palace Sapphire, Malad West
- Ashtalakshmi Parradise Chsl, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rashmi Icon | June 2026 | August 2028 | 0% | 1 unit booked out of 51 units for sale |
| Brahmand | May 2026 | December 2031 | 0% | 0 units booked out of 49 units for sale |
| Ambit Iconia | October 2026 | March 2031 | 0% | 0 units booked out of 66 units for sale |
| Palace Sapphire | October 2026 | October 2031 | 0% | 0 units booked out of 46 units for sale |
| Ashtalakshmi Parradise Chsl | March 2026 | December 2029 | 0% | 0 units booked out of 44 units for sale |
About this project
Rustomjee Ozone Skye by Keystone Realtors Limited (Rustomjee) is a 128-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in July 2026 with possession due in April 2032. 0 units booked out of total 128 units. Work on the concrete structure (RCC) has not started.
Read full summary
Rustomjee Ozone Skye is an SRA-sanctioned project by Keystone Realtors Limited in Malad West, Mumbai 400064, registered with MahaRERA as PR1180002601227. It was launched in July 2026. It has 128 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2032, extended by 4 months from the original December 2031. Construction: excavation not started, structure (RCC) not started, final finishes not started.
0 units booked out of total 128 units (0%).
Rustomjee's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 38 |
|---|---|
| Total units across these projects | 3,435 |
| Completed without extending the possession date | 15 |
| Completed after an extension | 2 |
| Lapsed | 5 |
| Under construction | 16 |
| Possession date extended on the builder's application | 8 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Rustomjee projects | 119 (11 of 38 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.