Runwal Westwind Heights, Khar West
by Ariane Orgachem Private Limited · Khar West, Mumbai 400052 · Map
- Launched
- Apr 20262 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 29 of 6545% · 15 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale29 booked out of 65 units
Rehab15 units for existing members
Total 80 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 30
- 2 BHK
- 19
- 3 BHK
- 15
- Other units
- 16
- Total units
- 80
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 65
- Rehab units
- 15
- Reserved units
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 30% | 0% | 29 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400052
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Sep 2029 |
| Concrete structure (RCC) | 30% | 0% |
| Units booked (free sale) | 45% | 29% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- The Address By Sach, Khar West
- 32 Elements, Khar West
- Crest Uno, Khar West
- Royce Residences, Khar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Address By Sach | March 2026 | May 2029 | 0% | 0 units booked out of 9 units for sale |
| 32 Elements | February 2026 | April 2029 | 0% | 1 unit booked out of 19 units for sale |
| Crest Uno | June 2026 | December 2029 | 0% | 20 units booked out of 28 units for sale |
| Royce Residences | January 2026 | June 2030 | 5% | 11 units booked out of 21 units for sale |
About this project
Runwal Westwind Heights by Ariane Orgachem Private Limited (Runwal) is an 80-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in April 2026 with possession due in December 2028. 29 units booked out of 65 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Runwal Westwind Heights is a BMC-sanctioned project by Ariane Orgachem Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as PM1180002600031. It was launched in April 2026. It has 80 units in 1 building: 64 homes (1, 2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 80 units, 65 are for sale and 15 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.
29 units booked out of 65 units for sale (45%). Since the July 2026 update, 29 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 30%.
Runwal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.