Skip to main content

Royce Residences, Khar West

by Maxrich Infra Private Limited · Khar West, Mumbai 400052 · Map

Launched
Jan 20264 yrs 5 mths promised
Possession (MahaRERA)
Jun 2030Not extended
Concrete structure
5%Mid-construction
Booked (free sale)
11 of 2152% · 12 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 21 units

Rehab12 units for existing members

Total 33 units. Rehab units are not for sale.

Project facts

1 BHK
13
2 BHK
12
3 BHK
8
Total units
33
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
21
Rehab units
12
Reserved units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)5%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 5%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 5%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%5%0%11
100%5%0%11

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400052

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 5 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2030Sep 2029
Concrete structure (RCC)5%0%
Units booked (free sale)52%10%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Royce Residences by Maxrich Infra Private Limited is a 33-unit SRA-sanctioned project in Khar West, Mumbai 400052, launched in January 2026 with possession due in June 2030. 11 units booked out of 21 units for sale. The concrete structure (RCC) is 5% complete.

Read full summary

Royce Residences is an SRA-sanctioned project by Maxrich Infra Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as PR1180002502067. It was launched in January 2026. It has 33 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 21 are for sale and 12 are rehab units for existing members.

Its registered possession date is June 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.

11 units booked out of 21 units for sale (52%).