Pearl Elegance, Mahim
by Pearl Concept Realty LLP · Mahim, Mumbai 400016 · Map
- Launched
- Jul 20253 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 4 of 1822% · 16 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 18 units
Rehab16 units for existing members
Total 34 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 18
- 2 BHK
- 16
- Total units
- 34
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 4 | |
| 100% | 12% | 0% | 2 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400016
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Mar 2029 |
| Concrete structure (RCC) | 50% | 10% |
| Units booked (free sale) | 22% | 24% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Avissa, Mahim
- Shree Nav Dadar, Mahim
- The Redevelopment Of Kirti Mandir Chsl, Mahim
- Aakasa Shivaji Park, Mahim
- Shree Krishnakunj, Mahim
- Ethics Oliver, Mahim
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Avissa | June 2025 | December 2029 | 50% | 0 units booked out of 8 units for sale |
| Shree Nav Dadar | June 2025 | December 2027 | 82% | 0 units booked out of 2 units for sale |
| The Redevelopment Of Kirti Mandir Chsl | October 2025 | April 2029 | 0% | 7 units booked out of 21 units for sale |
| Aakasa Shivaji Park | October 2025 | March 2029 | 0% | 13 units booked out of 16 units for sale |
| Shree Krishnakunj | October 2025 | November 2028 | 20% | 3 units booked out of 7 units for sale |
| Ethics Oliver | October 2025 | December 2029 | 0% | 2 units booked out of 14 units for sale |
About this project
Pearl Elegance by Pearl Concept Realty LLP is a 34-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in July 2025 with possession due in December 2028. 4 units booked out of 18 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
Pearl Elegance is a BMC-sanctioned project by Pearl Concept Realty LLP in Mahim, Mumbai 400016, registered with MahaRERA as PR1170002500367. It was launched in July 2025. It has 34 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 18 are for sale and 16 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.
4 units booked out of 18 units for sale (22%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 12% to 50%.