Ethics Oliver, Mahim

by Chaitanya Developers · Mahim, Mumbai 400016 · Map

Launched
Oct 20254 yrs 2 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
2 of 1414% · 37 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 14 units

Rehab37 units for existing members

Total 51 units. Rehab units are not for sale.

Project facts

1 RK
1
2 BHK
37
3 BHK
12
4 BHK
1
Total units
51
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 90%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%2
90%0%0%1
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400016

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400016
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths3 yrs 5 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Mar 2029
Concrete structure (RCC)0%0%
Units booked (free sale)14%28%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ethics Oliver by Chaitanya Developers is a 51-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in October 2025 with possession due in December 2029. 2 units booked out of 14 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Ethics Oliver is a BMC-sanctioned project by Chaitanya Developers in Mahim, Mumbai 400016, registered with MahaRERA as PR1170002501231. It was launched in October 2025. It has 51 units in 1 building, with 1 RK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 51 units, 14 are for sale and 37 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

2 units booked out of 14 units for sale (14%). Since the July 2026 update, 1 more unit has been booked.