Sapphire By Geecee, Andheri West

by GeeCee Ventures Limited · Andheri West, Mumbai 400053 · Map

Launched
Jun 20254 yrs promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
7%Mid-construction
Booked (free sale)
0 of 530% · 48 rehab units
Buildings
30.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 53 units

Rehab48 units for existing members

Total 101 units. Rehab units are not for sale.

Project facts

2 BHK
50
3 BHK
50
5+ BHK
1
Total units
101
Buildings
3
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
53
Rehab units
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)7%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 43%Jul 2026: Excavation 85%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 7%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 7%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%7%0%0
85%0%0%0
43%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400053

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs3 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2029Dec 2028
Concrete structure (RCC)7%3%
Units booked (free sale)0%42%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sapphire By Geecee by GeeCee Ventures Limited is a 101-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in June 2025 with possession due in June 2029. 0 units booked out of 53 units for sale. The concrete structure (RCC) is 7% complete.

Read full summary

Sapphire By Geecee is a BMC-sanctioned project by GeeCee Ventures Limited in Andheri West, Mumbai 400053, registered with MahaRERA as PR1180002500067. It was launched in June 2025. It has 101 units in 3 buildings, with 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 101 units, 53 are for sale and 48 are rehab units for existing members.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 7% complete, final finishes not started.

0 units booked out of 53 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 7%.