Shree Vani, Chembur

by Shree Krishna Properties · Chembur, Mumbai 400071 · Map

Launched
Sep 20252 yrs 6 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
50%Mid-construction
Booked (free sale)
0 of 70% · 11 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 7 units

Rehab11 units for existing members

Total 18 units. Rehab units are not for sale.

Project facts

2 BHK
8
3 BHK
7
4 BHK
3
Total units
18
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
7
Rehab units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 50%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%0
100%50%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths2 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028Sep 2028
Concrete structure (RCC)50%78%
Units booked (free sale)0%57%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shree Vani by Shree Krishna Properties is an 18-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in September 2025 with possession due in March 2028. 0 units booked out of 7 units for sale. The concrete structure (RCC) is 50% complete.

Read full summary

Shree Vani is a BMC-sanctioned project by Shree Krishna Properties in Chembur, Mumbai 400071, registered with MahaRERA as PR1180002501019. It was launched in September 2025. It has 18 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 7 are for sale and 11 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

0 units booked out of 7 units for sale (0%).