Sarayu Sabari, Chembur
by Majestic Royale Developers · Chembur, Mumbai 400071 · Map
- Launched
- May 20253 yrs 5 mths promised
- Possession (MahaRERA)
- Oct 2028Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 2 of 2100% · 20 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 2 units
Rehab20 units for existing members
Total 22 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 5
- 2 BHK
- 5
- 3 BHK
- 12
- Total units
- 22
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 2
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 2 | |
| 100% | 40% | 0% | 1 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Oct 2028 | May 2028 |
| Concrete structure (RCC) | 90% | 80% |
| Units booked (free sale) | 100% | 40% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- The Harvest, Chembur
- Shree Venkateswara CHSL, Chembur
- Kedarnath, Chembur
- Pardis Chitragandha, Chembur
- Shree Vani, Chembur
- Sai Saburi, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Harvest | May 2025 | June 2028 | 100% | 5 units booked out of 17 units for sale |
| Shree Venkateswara CHSL | March 2025 | October 2027 | 80% | 1 unit booked out of 2 units for sale |
| Kedarnath | February 2025 | December 2028 | 80% | 7 units booked out of 13 units for sale |
| Pardis Chitragandha | January 2025 | December 2028 | 77% | 3 units booked out of 11 units for sale |
| Shree Vani | September 2025 | March 2028 | 50% | 0 units booked out of 7 units for sale |
| Sai Saburi | September 2025 | December 2027 | 100% | 8 units booked out of 9 units for sale |
About this project
Sarayu Sabari by Majestic Royale Developers is a 22-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in May 2025 with possession due in October 2028. 2 units booked out of 2 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Sarayu Sabari is a BMC-sanctioned project by Majestic Royale Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51800080150. It was launched in May 2025. It has 22 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 2 are for sale and 20 are rehab units for existing members.
Its registered possession date is October 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
2 units booked out of 2 units for sale (100%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 40% to 90%.