Sai Saburi, Chembur

by Pardis LA LLP · Chembur, Mumbai 400071 · Map

Launched
Sep 20252 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
8 of 989%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 9 units

Land-owner share7 units, not for sale

Total 16 units. Land-owner units are not for sale.

Project facts

1 BHK
9
2 BHK
6
4 BHK
1
Total units
16
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Land-owner share (not for sale)
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%8
100%80%0%3
100%10%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths2 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Jul 2028
Concrete structure (RCC)100%72%
Units booked (free sale)89%48%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sai Saburi by Pardis LA LLP is a 16-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in September 2025 with possession due in December 2027. 8 units booked out of 9 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sai Saburi is a BMC-sanctioned project by Pardis LA LLP in Chembur, Mumbai 400071, registered with MahaRERA as PR1180002500747. It was launched in September 2025. It has 16 units in 1 building, with 1, 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 16 units, 9 are for sale and 7 are the land-owner's share, not for sale.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

8 units booked out of 9 units for sale (89%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 100%.