Jaydeep One, Mulund East
by Trinity Creative Homes LLP · Mulund East, Mumbai 400081 · Map
- Launched
- Oct 20253 yrs 5 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 39 of 15425% · 60 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale39 booked out of 154 units
Rehab60 units for existing members
Total 214 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 36
- 2 BHK
- 178
- Total units
- 214
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 154
- Rehab units
- 60
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 39 | |
| 100% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400081
Projects with 100–450 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 3 yrs 9 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Mar 2029 | Mar 2029 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 25% | 62% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Shraddha Phoenix, Mulund East
- HS Emerald, Mulund East
- HS Heritage, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shraddha Phoenix | April 2026 | December 2029 | 0% | 4 units booked out of 120 units for sale |
| HS Emerald | March 2025 | December 2028 | 0% | 72 units booked out of 116 units for sale |
| HS Heritage | February 2025 | March 2029 | 0% | 77 units booked out of 109 units for sale |
About this project
Jaydeep One by Trinity Creative Homes LLP is a 214-unit MHADA-sanctioned project in Mulund East, Mumbai 400081, launched in October 2025 with possession due in March 2029. 39 units booked out of 154 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Jaydeep One is a MHADA-sanctioned project by Trinity Creative Homes LLP in Mulund East, Mumbai 400081, registered with MahaRERA as PR1180002501048. It was launched in October 2025. It has 214 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 214 units, 154 are for sale and 60 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
39 units booked out of 154 units for sale (25%).