Shraddha Phoenix, Mulund East
by Shraddha Prime Projects Limited · Mulund East, Mumbai 400081 · Map
- Launched
- Apr 20263 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 4 of 1203% · 105 rehab units
- Buildings
- 30.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 120 units
Rehab105 units for existing members
Total 225 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 190
- 2 BHK
- 28
- Other units
- 7
- Total units
- 225
- Buildings
- 3
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 120
- Rehab units
- 105
- Reserved units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 4 | |
| 0% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400081
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 4 yrs 6 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2029 | Dec 2030 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 3% | 25% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Mulund Shriram Co-Operative Housing Society Limited, Mulund East
- Jaydeep One, Mulund East
- East 7 Residences, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mulund Shriram Co-Operative Housing Society Limited | June 2026 | December 2030 | 0% | 0 units booked out of 79 units for sale |
| Jaydeep One | October 2025 | March 2029 | 0% | 39 units booked out of 154 units for sale |
| East 7 Residences | October 2026 | July 2031 | 0% | 38 units booked out of 64 units for sale |
About this project
Shraddha Phoenix by Shraddha Prime Projects Limited is a 225-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in April 2026 with possession due in December 2029. 4 units booked out of 120 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Shraddha Phoenix is an SRA-sanctioned project by Shraddha Prime Projects Limited in Mulund East, Mumbai 400081, registered with MahaRERA as PR1180002600141. It was launched in April 2026. It has 225 units in 3 buildings: 218 homes (1 and 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 225 units, 120 are for sale and 105 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
4 units booked out of 120 units for sale (3%). Since the July 2026 update, 3 more units have been booked.
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.