New Parvati Apartment, Dahisar

by M/S Gagangiri Developers · Dahisar, Mumbai 400068 · Map

Launched
Feb 20262 yrs 10 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
15%Mid-construction
Booked (free sale)
4 of 1233% · 37 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 12 units

Rehab37 units for existing members

Total 49 units. Rehab units are not for sale.

Project facts

1 BHK
28
2 BHK
17
Other units
4
Total units
49
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)15%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 15%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 15%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%4
100%0%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths2 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Oct 2028
Concrete structure (RCC)15%24%
Units booked (free sale)33%11%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

New Parvati Apartment by M/S Gagangiri Developers is a 49-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in February 2026 with possession due in December 2028. 4 units booked out of 12 units for sale. The concrete structure (RCC) is 15% complete.

Read full summary

New Parvati Apartment is a BMC-sanctioned project by M/S Gagangiri Developers in Dahisar, Mumbai 400068, registered with MahaRERA as PM1180002502407. It was launched in February 2026. It has 49 units in 1 building: 45 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 12 are for sale and 37 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.

4 units booked out of 12 units for sale (33%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 15%.