Skip to main content

BRIGHTLAND Co-operative Housing society Ltd, Khar West

by LN Realtors and Developers LLP · Khar West, Mumbai 400052 · Map

Launched
Apr 20262 yrs 2 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 40% · 11 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 4 units

Rehab11 units for existing members

Total 15 units. Rehab units are not for sale.

Project facts

1 BHK
4
3 BHK
9
Other units
2
Total units
15
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
4
Rehab units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400052

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 2 mths3 yrs 6 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Jun 2028Dec 2029
Concrete structure (RCC)0%0%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

BRIGHTLAND Co-operative Housing society Ltd by LN Realtors and Developers LLP is a 15-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in April 2026 with possession due in June 2028. 0 units booked out of 4 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

BRIGHTLAND Co-operative Housing society Ltd is a BMC-sanctioned project by LN Realtors and Developers LLP in Khar West, Mumbai 400052, registered with MahaRERA as PR1180002600294. It was launched in April 2026. It has 15 units in 1 building: 13 homes (1 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 15 units, 4 are for sale and 11 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 4 units for sale (0%).