Rishabraj Pooja, Khar West
by Rishabraj Estate LLP · Khar West, Mumbai 400052 · Map
- Launched
- Feb 20263 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 60% · 24 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 6 units
Rehab24 units for existing members
Total 30 units. Rehab units are not for sale.
Project facts
- 3 BHK
- 24
- Other units
- 6
- Total units
- 30
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 0 | |
| 50% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400052
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Sep 2029 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 0% | 19% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- 32 Elements, Khar West
- Spectrum, Khar West
- Royce Residences, Khar West
- The Address By Sach, Khar West
- BRIGHTLAND Co-operative Housing society Ltd, Khar West
- Namrata, Khar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| 32 Elements | February 2026 | April 2029 | 0% | 1 unit booked out of 19 units for sale |
| Spectrum | January 2026 | December 2030 | 5% | 3 units booked out of 9 units for sale |
| Royce Residences | January 2026 | June 2030 | 5% | 11 units booked out of 21 units for sale |
| The Address By Sach | March 2026 | May 2029 | 0% | 0 units booked out of 9 units for sale |
| BRIGHTLAND Co-operative Housing society Ltd | April 2026 | June 2028 | 0% | 0 units booked out of 4 units for sale |
| Namrata | June 2026 | December 2029 | 0% | 3 units booked out of 7 units for sale |
About this project
Rishabraj Pooja by Rishabraj Estate LLP is a 30-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in February 2026 with possession due in December 2029. 0 units booked out of 6 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Rishabraj Pooja is a BMC-sanctioned project by Rishabraj Estate LLP in Khar West, Mumbai 400052, registered with MahaRERA as PM1180002502312. It was launched in February 2026. It has 30 units in 1 building: 24 homes (3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 6 are for sale and 24 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
0 units booked out of 6 units for sale (0%).
Rishabraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 43 |
|---|---|
| Total units across these projects | 1,514 |
| Completed without extending the possession date | 22 |
| Completed after an extension | 3 |
| Lapsed | 3 |
| Under construction | 15 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 2 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Rishabraj projects | 33 (4 of 43 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.