Spectrum, Khar West

by Elite Housing LLP · Khar West, Mumbai 400052 · Map

Launched
Jan 20264 yrs 11 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
5%Mid-construction
Booked (free sale)
3 of 933% · 20 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 9 units

Rehab20 units for existing members

Total 29 units. Rehab units are not for sale.

Project facts

3 BHK
24
4 BHK
5
Total units
29
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)5%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 5%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 5%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%5%0%3
100%0%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400052

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths3 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2030Sep 2029
Concrete structure (RCC)5%0%
Units booked (free sale)33%3%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Spectrum by Elite Housing LLP is a 29-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in January 2026 with possession due in December 2030. 3 units booked out of 9 units for sale. The concrete structure (RCC) is 5% complete.

Read full summary

Spectrum is a BMC-sanctioned project by Elite Housing LLP in Khar West, Mumbai 400052, registered with MahaRERA as PR1180002502121. It was launched in January 2026. It has 29 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 9 are for sale and 20 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.

3 units booked out of 9 units for sale (33%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 5%.