Dahisar Garden View, Dahisar
by Vallabh Vihaan Shreeji Constructions · Dahisar, Mumbai 400068 · Map
- Launched
- Jun 20262 yrs 9 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 9 of 2536% · 10 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 25 units
Rehab10 units for existing members
Total 35 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 9
- 3 BHK
- 6
- Total units
- 35
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 25
- Rehab units
- 10
- Reserved units
- 9
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 9 | |
| 0% | 0% | 0% | 9 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400068
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 2 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2029 | Sep 2029 |
| Concrete structure (RCC) | 0% | 1% |
| Units booked (free sale) | 36% | 2% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Prime Orchid, Dahisar
- Mpr Supreme, Dahisar
- Jdj Jewel, Dahisar
- Parvatraji, Dahisar
- Dani Aroma, Dahisar
- Om Siddharth Chsl, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Prime Orchid | June 2026 | December 2029 | 0% | 1 unit booked out of 21 units for sale |
| Mpr Supreme | May 2026 | December 2028 | 0% | 12 units booked out of 30 units for sale |
| Jdj Jewel | April 2026 | January 2031 | 2% | 2 units booked out of 12 units for sale |
| Parvatraji | April 2026 | June 2028 | 60% | 0 units booked out of 17 units for sale |
| Dani Aroma | October 2026 | September 2029 | 0% | 0 units booked out of 20 units for sale |
| Om Siddharth Chsl | October 2026 | September 2029 | 18% | 0 units booked out of 5 units for sale |
About this project
Dahisar Garden View by Vallabh Vihaan Shreeji Constructions is a 35-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in June 2026 with possession due in March 2029. 9 units booked out of 25 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Dahisar Garden View is a BMC-sanctioned project by Vallabh Vihaan Shreeji Constructions in Dahisar, Mumbai 400068, registered with MahaRERA as PR1180002600588. It was launched in June 2026. It has 35 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 25 are for sale and 10 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
9 units booked out of 25 units for sale (36%).