Skip to main content

Parvatraji, Dahisar

by Prime Group LLP · Dahisar, Mumbai 400068 · Map

Launched
Apr 20262 yrs 2 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
0 of 170% · 11 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 17 units

Rehab11 units for existing members

Total 28 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
21
3 BHK
1
Total units
28
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
17
Rehab units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 30%Oct 2026: Concrete structure (RCC) 60%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%0
100%30%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 2 mths2 yrs 8 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Jun 2028Dec 2028
Concrete structure (RCC)60%1%
Units booked (free sale)0%25%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Parvatraji by Prime Group LLP is a 28-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in April 2026 with possession due in June 2028. 0 units booked out of 17 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Parvatraji is a BMC-sanctioned project by Prime Group LLP in Dahisar, Mumbai 400068, registered with MahaRERA as PR1180002600116. It was launched in April 2026. It has 28 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 17 are for sale and 11 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

0 units booked out of 17 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 30% to 60%.