Jdj Jewel, Dahisar

by Jdj Housing · Dahisar, Mumbai 400068 · Map

Launched
Apr 20264 yrs 9 mths promised
Possession (MahaRERA)
Jan 2031Not extended
Concrete structure
2%Mid-construction
Booked (free sale)
2 of 1217% · 37 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 12 units

Rehab37 units for existing members

Total 49 units. Rehab units are not for sale.

Project facts

1 BHK
12
2 BHK
18
Other units
19
Total units
49
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)2%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 2%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 2%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%2%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths2 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jan 2031Dec 2028
Concrete structure (RCC)2%8%
Units booked (free sale)17%24%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Jdj Jewel by Jdj Housing is a 49-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in April 2026 with possession due in January 2031. 2 units booked out of 12 units for sale. The concrete structure (RCC) is 2% complete.

Read full summary

Jdj Jewel is a BMC-sanctioned project by Jdj Housing in Dahisar, Mumbai 400068, registered with MahaRERA as PM1180002600191. It was launched in April 2026. It has 49 units in 2 buildings: 30 homes (1 and 2 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 12 are for sale and 37 are rehab units for existing members.

Its registered possession date is January 2031, unchanged since launch. Construction: excavation complete, structure (RCC) 2% complete, final finishes not started.

2 units booked out of 12 units for sale (17%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 2%.