Skip to main content

Destination (D R Gavhane) projects in Pune

MahaRERA projects by Destination (D R Gavhane) registered 2017–2025 in Pune & PCMC.

Projects registered with MahaRERA17
Total units across these projects1,343
Full record

MahaRERA projects registered 2017–2025 in Pune & PCMC

Completed without extending the possession date7
Completed after an extension0
Lapsed3
Under construction7
Possession date extended on the builder's application1
Typical time from launch to 100% structure2 years 6 months
MahaRERA complaints (filed by or against the builder), all Destination (D R Gavhane) projects1 (1 of 17 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Moshi (2) · Charholi Budruk (2) · Dudulgaon (1)

Under construction

ProjectVillageStagePossessionBooked
Destination 12 GemsCharholi BudrukMid-constructionJuly 20272 units booked out of total 13 units
Destination 24 Avenue · 3 phasesCharholi BudrukReady to moveMar 2026 – Mar 2027226 units booked out of total 357 units
Destination Ostia Building E1DudulgaonNearing possessionApril 202796 units booked out of total 120 units
Completed
ProjectVillageStatus
Destination 24 AvenueCharholi BudrukCompleted
Destination AnanyaMoshiCompleted
Destination MemoirChikhaliCompleted
Destination OsiyanCharholi BudrukCompleted
Destination OstiaMoshiCompleted
Lapsed
ProjectVillageStatus
Destination OstiaMoshiLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us