Destination 24 Avenue, Charholi
by D R Gavhane Landmarks LLP. Charholi, Pune 412105. View on Google Maps
- Launched
- First of 3 phases
- Possession dates (MahaRERA)
- Dec 2025 – Mar 2027varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 100%Nearing possession3 of 3 phases with structure completeWeighted across 3 phases
- Units booked
- 158 of 35744% booked
- Price per sq ft
- ₹6,0002026 salesdown 2% on 2025See what buyers paid
Facts
Project facts
| 1 BHK | 134 |
|---|---|
| 2 BHK | 116 |
| 3 BHK | 37 |
| 4 BHK | 11 |
| 5+ BHK | 1 |
| Total units | 357 |
| Buildings | 3 |
| Land | 0.2 acres |
| Phases | 3 |
Since Dec 2025: booked 160 → 158
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 2 BHK | about 640 – 800 sq ft | ₹39 – 43 lakh | 2026 sales |
Price per sq ft, year by year
| 2025 | ₹6,100 per sq ft |
|---|---|
| 2026down 2% on 2025 | ₹6,000 per sq ft |
Studios (under 450 sq ft): ₹4,600 per sq ft in 2025 sales, up 5% on 2024. Sizes about 320 – 390 sq ft.
Registered sales across all 3 phases.
Compared with the typical Charholi rate in 2026: about 40% lower
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Studios are priced separately from flats and are not used in area price comparisons or on the Property rates page.
Phases
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Destination 24 Avenue C Building Ready to move Lapsed | P52100032909 | 133 | 100% | 80% | |
| Destination 24 Avenue B Building Ready to move Lapsed | P52100047564 | 96 | 100% | 17% | |
| Destination 24 Avenue A Building Nearing possession | P52100056255 | 70 | 100% | 3% |
Show updates by phase
Destination 24 Avenue C Building (P52100032909)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 136 | |
| 100% | 100% | 0% | 138 | |
| 100% | 100% | 0% | 77 | |
| 100% | 72% | 0% | 46 |
"—" means MahaRERA shows no figure for that update.
Destination 24 Avenue B Building (P52100047564)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 20 | |
| 100% | 100% | 95% | 20 | |
| 100% | 100% | 0% | 19 | |
| 100% | 100% | 0% | 3 | |
| 100% | 0% | 0% | 3 |
"—" means MahaRERA shows no figure for that update.
Destination 24 Avenue A Building (P52100056255)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 2 | |
| 100% | 8% | 0% | 2 | |
| 100% | 8% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 6 similar projects in PIN 412105
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 4 mths | 3 yrs 8 mths |
| Possession date extended | No | 5 of 6 |
| Possession date (MahaRERA) | Dec 2025 – Mar 2027 | November 2026 |
| Concrete structure (RCC) | 100% | 98% |
| Units booked | 44% | 73% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Omkar Residency | February 2022 | September 2026 | 100% | 155 of 210 booked (74%) |
| Utopia Gold | February 2022 | June 2026 | 96% | 460 of 544 booked (85%) |
| Aksha Ambar | January 2022 | Jun 2025 – Dec 2027 | 100% | 208 of 290 booked (72%) |
| Dwaarka World PH 1 | January 2022 | December 2026 | 100% | 248 of 497 booked (50%) |
| Kesar Treetown Phase 3 | May 2022 | December 2026 | 67% | 259 of 291 booked (89%) |
| Kartiki Heights | May 2022 | Dec 2028 | 80% | 128 of 191 booked (67%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Destination 24 Avenue is a project by D R Gavhane Landmarks LLP in Charholi, Pune 412105, registered with MahaRERA as 3 phases (P52100032909, P52100047564, P52100056255). The first phase was launched in February 2022. Together the phases have 357 units in 3 buildings, with 1, 2, 3, 4 & 5+ BHK homes as registered with MahaRERA. On MahaRERA, 2 are lapsed and 1 is active.
The phases' registered possession dates run from December 2025 to March 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 84% complete. 3 of the 3 phases have their structure complete.
158 of the 357 units reported for sale are booked (44%). In 2026 registered sales, 80% of flats here sold at ₹6,000 per sq ft or less (down 2% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 40% lower than the typical Charholi rate in 2026. Most buyers paid ₹39–43 lakh for 2 BHK flats of about 640–800 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra. Its studios (under 450 sq ft) sold at ₹4,600 per sq ft or less in 2025; studios are priced separately from flats.