Ellora projects in Pune
MahaRERA projects by Ellora registered 2017–2026 in Pune & PCMC.
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 1,443 |
Full record
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Completed without extending the possession date | 7 |
|---|---|
| Completed after an extension | 1 |
| Lapsed | 3 |
| Under construction | 6 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 3 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Ellora projects | 1 (1 of 17 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Chikhali (2) · Moshi (1) · Pimpri (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Ellora Enclave | Pimpri | Early stage | July 2028 | 9 units booked out of total 16 units |
| Nakshatra I Land · 6 phases | Moshi | Mid-construction | Dec 2026 – Jul 2029 | 472 units booked out of total 664 units |
| Privia Naimish | Chikhali | Mid-construction | December 2028 | 2 units booked out of total 26 units |
Completed
| Project | Village | Status |
|---|---|---|
| Ellora Shopee | Bhosari | Completed |
| Nakshatra I-Land | Moshi | Completed |
| Privia 9 | Moshi | Completed |
| Privia Square | Moshi | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Privia Prestige | Chikhali | Lapsed |
| Privia Square | Moshi | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.