Nakshatra I Land, Moshi
by Ellora Buildwell Pvt Ltd. Moshi, Pune 412105. View on Google Maps
- Launched
- First of 3 phases
- Possession dates (MahaRERA)
- Jun 2026 – Dec 2027varies by phase1 of 3 phases have an extended possession date. Reading a project's possession date
- Concrete structure (RCC)
- 16%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
- Units booked
- 282 of 39372% booked290 homes + 103 other units
Facts
Project facts
| 1 BHK | 5 |
|---|---|
| 2 BHK | 260 |
| 3 BHK | 25 |
| Total units | 393 |
| Buildings | 4 |
| Land | 1 acres |
| Phases | 3 |
Shortlist 2 or more to compare side by side.
Phases
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Nakshatra I Land Phase 3 Mid-construction Lapsed | P52100046609 | 95 | 50% | 100% | |
| Nakshatra i Land Phase 5 Early stage | P52100050468 | 190 | 0% | 92% | |
| Nakshatra i Land Phase - 7 Early stage | P52100056189 | 5 | 0% | 12% |
Show updates by phase
Nakshatra I Land Phase 3 (P52100046609)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 95 | |
| 100% | 50% | 0% | 66 |
"—" means MahaRERA shows no figure for that update.
Nakshatra i Land Phase 5 (P52100050468)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 0% | 0% | 174 | |
| 50% | 0% | 0% | 2 | |
| 0% | 0% | 0% | 1 |
"—" means MahaRERA shows no figure for that update.
Nakshatra i Land Phase - 7 (P52100056189)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 13 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 6 similar projects in PIN 412105
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 8 mths | 3 yrs 8 mths |
| Possession date extended | Yes | 2 of 6 |
| Possession date (MahaRERA) | Jun 2026 – Dec 2027 | September 2026 |
| Concrete structure (RCC) | 16% | 85% |
| Units booked | 72% | 85% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Soho | August 2022 | April 2026 | 100% | All 363 units booked |
| Kosmas | August 2022 | Dec 2026 – Dec 2027 | 60% | 73 of 115 booked (63%) |
| Shri Icon | August 2022 | December 2026 | 80% | 69 of 183 booked (38%) |
| Nakshatra i-Land | September 2022 | Jun 2026 – Dec 2026 | 30% | 190 of 190 booked (100%) |
| River Nest | September 2022 | Jun 2026 – Jun 2027 | 90% | 353 of 433 booked (82%) |
| Ravikiran Annexe | June 2022 | Feb 2028 | 100% | 279 of 313 booked (89%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Nakshatra I Land is a project by Ellora Buildwell Pvt Ltd in Moshi, Pune 412105, registered with MahaRERA as 3 phases (P52100046609, P52100050468, P52100056189). The first phase was launched in August 2022. Together the phases have 393 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is lapsed.
The phases' registered possession dates run from June 2026 to December 2027; 1 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 16% complete and final finishes 0% complete. 0 of the 3 phases have their structure complete.
282 of the 393 units reported for sale are booked (72%).