Kakkad projects in Pune
MahaRERA projects by Kakkad registered 2019–2025 in Pune & PCMC.
| Projects registered with MahaRERA | 8 |
|---|---|
| Total units across these projects | 1,052 |
Full record
MahaRERA projects registered 2019–2025 in Pune & PCMC
| Completed without extending the possession date | 2 |
|---|---|
| Completed after an extension | 0 |
| Lapsed | 1 |
| Under construction | 5 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 4 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Kakkad projects | 2 (2 of 8 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Balewadi (1) · Ambegaon Budruk (1) · Wanowrie (1) · Erandwane (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Bella Casa - Phase 1 | Ambegaon Budruk | Nearing possession | December 2026 | 335 units booked out of total 346 units |
| Kailash Kutir PHASE-2 | Wanowrie | Nearing possession | September 2027 | 59 units booked out of total 72 units |
| Kakkad Orion | Erandwane | Early stage | December 2028 | 5 units booked out of total 6 units |
Completed
| Project | Village | Status |
|---|---|---|
| La Vida | Baner | Completed |
| Madhukosh | Balewadi | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| La Vida | Baner | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us