Marvel projects in Pune

MahaRERA projects by Marvel registered 2017–2022 in Pune & PCMC.

Projects registered with MahaRERA30
Total units across these projects1,815
Full record

MahaRERA projects registered 2017–2022 in Pune & PCMC

Completed without extending the possession date15
Completed after an extension5
Lapsed7
Under construction1
Not updated on MahaRERA for over a year2
Possession date extended on the builder's application11
Typical time from launch to 100% structure6 years 11 months
MahaRERA complaints (filed by or against the builder), all Marvel projects204 (23 of 30 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
  • Not updated on MahaRERA for over a year: the builder has not filed an update with MahaRERA for more than a year, so FlatNama cannot show a current status.

Where they build: Baner (1) · Mohammadwadi (1) · Lohegaon (1)

Under construction

ProjectVillageStagePossessionBooked
Marvel Isola J BuildingMohammadwadiNearing possessionDecember 202643 units booked out of total 44 units
Completed
ProjectVillageStatus
Marvel Arco BHadapsarCompleted
Marvel Arco EHadapsarCompleted
Marvel AurumGhorpadiCompleted
Marvel Bounty KHadapsarCompleted
Marvel BrisaBanerCompleted
Marvel Cascada CBanerCompleted
MARVEL CERISEKharadiCompleted
Marvel Citrine AKharadiCompleted
Marvel Fria P1, P2, P3WagholiCompleted
Marvel FuegoHadapsarCompleted
Marvel Ganga Sangria A,B,CMohammadwadiCompleted
Marvel Ganga Sangria D,EMohammadwadiCompleted
Marvel Ganga Sangria G,H,JMohammadwadiCompleted
Marvel Ganga Sangria K,L,MMohammadwadiCompleted
Marvel Ideal SpacioUndriCompleted
Marvel PiazzaLohegaonCompleted
Marvel Selva Ridge A,BBavdhan KhurdCompleted
Marvel Selva Ridge VillaBavdhan KhurdCompleted
Marvel ZephyrKharadiCompleted
Lapsed
ProjectVillageStatus
Marvel AquanasKharadiLapsed
Marvel BountyHadapsarLapsed
Marvel Cascada DBanerLapsed
Marvel Cascada EBanerLapsed
Marvel Diva UltimaHadapsarLapsed
Marvel Kyra A AND BHadapsarLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.