Mittal (Sun series) projects in Pune

MahaRERA projects by Mittal (Sun series) registered 2017–2026 in Pune & PCMC.

Projects registered with MahaRERA21
Total units across these projects3,090
Full record

MahaRERA projects registered 2017–2026 in Pune & PCMC

Completed without extending the possession date8
Completed after an extension2
Lapsed3
Under construction8
Possession date extended on the builder's application3
Typical time from launch to 100% structure2 years 6 months
MahaRERA complaints (filed by or against the builder), all Mittal (Sun series) projects5 (5 of 21 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Ambegaon Budruk (2) · Mundhwa (2) · Wadgaon Budruk (2) · Dhayari (1) · Kothrud (1) · Kharadi (1) · Sadashiv Peth (1)

Under construction

ProjectVillageStagePossessionBooked
Sun ApexAmbegaon BudrukEarly stageDecember 203012 units booked out of total 140 units
Sun EmeraldKharadiMid-constructionDecember 202969 units booked out of total 150 units
Sun GarnetMundhwaEarly stageDecember 20300 units booked out of total 129 units
Sun GlorySadashiv PethEarly stageMarch 203148 units booked out of total 96 units
Sun OrchidKothrudNearing possessionJune 202741 units booked out of total 48 units
Sun PlatinaMundhwaEarly stageMarch 20300 units booked out of total 21 units
Sun RegaliaWadgaon BudrukMid-constructionDecember 203091 units booked out of total 147 units
Sun TopazWadgaon BudrukEarly stageDecember 20310 units booked out of total 62 units
Completed
ProjectVillageStatus
Sun AuraWadgaon BudrukCompleted
Sun CityAmbegaon BudrukCompleted
Sun EnclaveWadgaon BudrukCompleted
Sun ExoticaYewalewadiCompleted
Sun HarmonyMoshiCompleted
Sun PlanetWadgaon BudrukCompleted
Sun RadiantKondhwa BudrukCompleted
Sun SapphireHadapsarCompleted
Lapsed
ProjectVillageStatus
Sun CityAmbegaon BudrukLapsed
Sun CrestDhayariLapsed
Sun VistaWadgaon BudrukLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us