Skip to main content
← Back

Sun Orchid, Kothrud

by Mittal Projects. Kothrud, Pune 411038. View on Google Maps

Launched
3 years 3 months promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
39 of 4881% booked
Price per sq ft (incl. balconies and terrace)
₹18,0002025 · 10 sales80% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK26
3 BHK22
Total units48
Buildings1
Land0.3 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 35 → 39 · final finishes 0% → 35%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹18,000 per sq ft10 sales

Rate vs other Kothrud projects, 2025: about 20% higher

Compared with 6 similar projects in PIN 411038

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 3 mths3 yrs 9 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)June 2027December 2027
Concrete structure (RCC) complete100%82%
Share of units booked81%26%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 7 months of the promised 3 years 3 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 35%Excavation 100%Concrete structure (RCC) 100%Final finishes 35%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%35%39
100%100%0%35
100%0%0%1
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Sun Orchid (MahaRERA P52100055156) is a residential project by Mittal Projects in Kothrud, Pune 411038. It was launched in March 2024. It has 48 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 35% complete. MahaRERA records do not show it as ready to move in.

39 of its 48 units are booked (81%). Since the December 2025 update, 4 more units have been booked. 80% of the 2025 sales we found here were at ₹18,000 per sq ft or less, counting balconies and terrace in the size, based on 10 registered sales. Buyers here paid a rate about 20% higher than at other Kothrud projects in 2025.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055156.Check it on MahaRERA (P52100055156)All projects in Kothrud