Raviraj projects in Pune

MahaRERA projects by Raviraj registered 2017–2025 in Pune & PCMC.

Projects registered with MahaRERA11
Total units across these projects1,005
Full record

MahaRERA projects registered 2017–2025 in Pune & PCMC

Completed without extending the possession date1
Completed after an extension6
Lapsed1
Under construction3
Possession date extended on the builder's application9
MahaRERA complaints (filed by or against the builder), all Raviraj projects1 (1 of 11 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Ghorpadi (1) · Kondhwa Budruk (1) · Ambegaon Khurd (1) · Erandwane (1)

Under construction

ProjectVillageStagePossessionBooked
15th Street AvenueErandwaneEarly stageJune 20279 units booked out of total 14 units
One Residency · 2 phasesAmbegaon KhurdMid-constructionMar 2027269 units booked out of total 355 units
Raviraj Splendour GreensKondhwa BudrukMid-constructionApril 202891 units booked out of total 215 units
Completed
ProjectVillageStatus
93 AvenueSopan BaugCompleted
AureatePimple SaudagarCompleted
GreenariaHadapsarCompleted
The Secret GardenGhorpadiCompleted
Lapsed
ProjectVillageStatus
AstriaKondhwa KhurdLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us