Raviraj Splendour Greens, Kondhwa Budruk
by Raviraj Sheth Developers LLP. Kondhwa Budruk, Pune 411048. View on Google Maps
- Launched
- 5 years originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 2 years 6 months (originally June 2024). Why possession dates change
- Concrete structure (RCC)
- 75%Mid-constructionAverage across 3 buildings
- Units booked
- 74 of 17642% booked
Project facts
| 1 RK | 1 |
|---|---|
| 1 BHK | 55 |
| 2 BHK | 120 |
| Total units | 176 |
| Buildings | 3 |
| Land | 1.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 32 → 74 · structure 47% → 75% · possession date June 2026 → December 2026
Compared with 4 similar projects in PIN 411048
Projects with 80–350 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs | 7 yrs 11 mths |
| Possession date extended | By 2 years 6 months | 1 of 4 |
| Possession date (MahaRERA) | December 2026 | January 2028 |
| Concrete structure (RCC) complete | 75% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shalimar Hillpark Phase III | January 2020 | June 2027 | 100% | 85 of 104 booked (82%) |
| Wellwisher Abode | February 2020 | December 2026 | 0% | 80 of 208 booked (38%) |
| Provident Kenvista T3 | April 2020 | September 2028 | 0% | Bookings not reported |
| Provident Kenvista T4 | April 2020 | September 2028 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 74 | |
| 100% | 47% | 0% | 32 | |
| 100% | 10% | 0% | 16 |
"—" means MahaRERA shows no figure for that update.
About this project
Raviraj Splendour Greens (MahaRERA P52100021159) is a residential project by Raviraj Sheth Developers LLP in Kondhwa Budruk, Pune 411048. It was launched in June 2019. It has 176 units in 3 buildings, with 1 RK, 1 BHK & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 2 years 6 months from the original June 2024. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 75% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
74 of its 176 units are booked (42%). Since the December 2025 update, 42 more units have been booked, the reported concrete structure (RCC) has gone from 47% to 75% and the possession date has moved from June 2026 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.