Solitaire (Classic Promoters) projects in Pune

MahaRERA projects by Solitaire (Classic Promoters) registered 2017–2025 in Pune & PCMC.

Projects registered with MahaRERA20
Total units across these projects2,641
Full record

MahaRERA projects registered 2017–2025 in Pune & PCMC

Completed without extending the possession date0
Completed after an extension5
Lapsed3
Under construction12
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years 8 months
MahaRERA complaints (filed by or against the builder), all Solitaire (Classic Promoters) projects165 (13 of 20 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Bibwewadi (4) · Dapodi (1)

Under construction

ProjectVillageStagePossessionBooked
Avalon City - C5 and C6 · 2 phasesDapodiNearing possessionMar 2027 – Nov 2027185 units booked out of total 193 units
World Four - Solitaire WorldBibwewadiMid-constructionSeptember 202738 units booked out of total 98 units
World One Solitaire WorldBibwewadiMid-constructionDecember 2026135 units booked out of total 185 units
World Three - Solitaire WorldBibwewadiReady to moveJune 2027124 units booked out of total 168 units
World Two - Solitaire WorldBibwewadiMid-constructionDecember 202654 units booked out of total 65 units
Completed
ProjectVillageStatus
Avalon City C-3DapodiCompleted
MudraGultekdiCompleted
PremierGultekdiCompleted
SBH Wakad C-3 1st and 2nd FloorWakadCompleted
Solitaire Business Hub KalyaninagarGhorpadiCompleted
Lapsed
ProjectVillageStatus
Solitaire Business Hub BanerBanerLapsed
Solitaire Business Hub Viman NagarLohegaonLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us