Solitaire (Classic Promoters) projects in Pune
MahaRERA projects by Solitaire (Classic Promoters) registered 2017–2025 in Pune & PCMC.
| Projects registered with MahaRERA | 20 |
|---|---|
| Total units across these projects | 2,641 |
Full record
MahaRERA projects registered 2017–2025 in Pune & PCMC
| Completed without extending the possession date | 0 |
|---|---|
| Completed after an extension | 5 |
| Lapsed | 3 |
| Under construction | 12 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Solitaire (Classic Promoters) projects | 165 (13 of 20 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Bibwewadi (4) · Dapodi (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Avalon City - C5 and C6 · 2 phases | Dapodi | Nearing possession | Mar 2027 – Nov 2027 | 185 units booked out of total 193 units |
| World Four - Solitaire World | Bibwewadi | Mid-construction | September 2027 | 38 units booked out of total 98 units |
| World One Solitaire World | Bibwewadi | Mid-construction | December 2026 | 135 units booked out of total 185 units |
| World Three - Solitaire World | Bibwewadi | Ready to move | June 2027 | 124 units booked out of total 168 units |
| World Two - Solitaire World | Bibwewadi | Mid-construction | December 2026 | 54 units booked out of total 65 units |
Completed
| Project | Village | Status |
|---|---|---|
| Avalon City C-3 | Dapodi | Completed |
| Mudra | Gultekdi | Completed |
| Premier | Gultekdi | Completed |
| SBH Wakad C-3 1st and 2nd Floor | Wakad | Completed |
| Solitaire Business Hub Kalyaninagar | Ghorpadi | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Solitaire Business Hub Baner | Baner | Lapsed |
| Solitaire Business Hub Viman Nagar | Lohegaon | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.