Skip to main content
← Back

Avalon City - C5 and C6, Dapodi

by Classic Promoters and Builders Private Limited. Dapodi, Pune 411012. View on Google Maps

Launched
4 years originally promised
Possession date (MahaRERA)
5 months awayExtended by 1 year (originally March 2026). Why possession dates change
Concrete structure (RCC)
100%Nearing possession
Units booked
101 of 10596% booked

Project facts

1 BHK38
2 BHK67
Total units105
Buildings1
Land1.6 acres
Complaints on MahaRERA (filed by or against the builder)3

Since Dec 2025: possession date March 2026 → March 2027 · complaints 2 → 3

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 20%Jun 2024: Concrete structure (RCC) 89%Dec 2024: Concrete structure (RCC) 89%Jun 2025: Concrete structure (RCC) 89%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%101
100%89%0%76
100%20%0%68

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Avalon City - C5 and C6 (MahaRERA P52100033855) is a residential project by Classic Promoters and Builders Private Limited in Dapodi, Pune 411012. It was launched in March 2022. It has 105 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.

101 of its 105 units are booked (96%). Since the December 2025 update, the possession date has moved from March 2026 to March 2027.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033855.Check it on MahaRERA (P52100033855)All projects in Dapodi