Xrbia projects in Pune
MahaRERA projects by Xrbia registered 2017–2019 in Pune & PCMC.
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 7,275 |
Full record
MahaRERA projects registered 2017–2019 in Pune & PCMC
| Completed without extending the possession date | 1 |
|---|---|
| Completed after an extension | 1 |
| Lapsed | 3 |
| Under construction | 4 |
| Possession date extended on the builder's application | 2 |
| MahaRERA complaints (filed by or against the builder), all Xrbia projects | 61 (9 of 9 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Kondhwa Khurd (1) · Charholi Budruk (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Millennium Park | Kondhwa Khurd | Nearing possession | December 2026 | 440 units booked out of total 645 units |
| SingaPune · 3 phases | Charholi Budruk | Mid-construction | Dec 2028 | 734 units booked out of total 2,268 units |
Completed
| Project | Village | Status |
|---|---|---|
| Xrbia Hinjewadi Road / Riverfront | Talegaon Dabhade | Completed |
| Xrbia Hinjewadi Road/Riverfront-Ph-1 | Talegaon Dabhade | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Xrbia Abode | Talegaon Dabhade | Lapsed |
| Xrbia Ambi | Ambi | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us