Ready and nearing possession in Dudulgaon
Nearing possession or ready to move: the concrete structure (RCC) is complete, or MahaRERA shows the project Completed.
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
17 projects
- Possession dates (MahaRERA)Jun 2025 – Dec 2027varies by phaseConcrete structure (RCC)100%Nearing possession2 of 2 phases with structure completeUnits booked217 units booked out of total 299 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Ready to moveFinal finishes 95% · completion not yet filed on MahaRERAUnits booked181 units booked out of total 242 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Nearing possessionUnits booked93 units booked out of total 120 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Ready to moveFinal finishes 100% · completion not yet filed on MahaRERAUnits booked94 units booked out of total 100 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Nearing possessionUnits booked62 units booked out of total 82 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Nearing possessionUnits booked67 units booked out of total 70 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Nearing possessionUnits booked32 units booked out of total 35 units
- Completed (MahaRERA)Completed (MahaRERA)Completion reported December 2025Concrete structure (RCC)100%Ready to moveUnits booked393 units booked out of total 572 units
- Possession dates (MahaRERA)Mar 2026Concrete structure (RCC)100%Nearing possession2 of 2 phases with structure completeUnits booked249 units booked out of total 249 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Nearing possessionUnits booked138 units booked out of total 147 units
- Completed (MahaRERA)Completed (MahaRERA)Completion reported July 2026Concrete structure (RCC)100%Ready to moveUnits booked123 units booked out of total 128 units
- Completed (MahaRERA)Completed (MahaRERA)Completion reported December 2025Concrete structure (RCC)100%Ready to moveUnits booked40 units booked out of total 123 units
- Completed (MahaRERA)Completed (MahaRERA)Completion reported December 2025Concrete structure (RCC)100%Ready to moveUnits booked89 units booked out of total 110 units
- Builder's MahaRERA dateBuilder's MahaRERA dateConcrete structure (RCC)100%Nearing possessionUnits booked93 units booked out of total 99 units
- Completed (MahaRERA)Completed (MahaRERA)Completion reported December 2025Concrete structure (RCC)100%Ready to moveUnits booked51 units booked out of total 91 units
- Completed (MahaRERA)Completed (MahaRERA)Completion reported December 2025Concrete structure (RCC)100%Ready to moveUnits booked40 units booked out of total 72 units
- Completed (MahaRERA)Completed (MahaRERA)Completion reported July 2026Concrete structure (RCC)100%Ready to moveUnits booked34 units booked out of total 48 units