Skip to main content
← Back

Anantam Skyone, Dudulgaon

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Rajshree Landmark LLP. Dudulgaon, Pune 412105. View on Google Maps

Launched
2 years 10 months originally promised
Possession date (MahaRERA)
This monthExtended by 10 months (originally December 2025). Why possession dates change
Concrete structure (RCC)
100%Finishing stage
Units booked
94 of 10094% booked

Project facts

1 BHK1
2 BHK44
3 BHK44
Other units (shops, offices or not given by type)11
Total units100
Buildings1
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 84 → 94 · final finishes 80% → 100% · possession date December 2025 → October 2026

Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths3 yrs 10 mths
Possession date extendedBy 10 months1 of 6
Possession date (MahaRERA)October 2026December 2026
Concrete structure (RCC) complete100%100%
Share of units booked94%82%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 10 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 20%Jun 2024: Concrete structure (RCC) 65%Dec 2024: Concrete structure (RCC) 65%Jun 2025: Concrete structure (RCC) 65%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 80%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%94
100%100%80%84
100%65%0%33
100%20%0%7

"—" means MahaRERA shows no figure for that update.

About this project

Anantam Skyone (MahaRERA P52100049675) is a residential project by Rajshree Landmark LLP in Dudulgaon, Pune 412105. It was launched in February 2023. It has 100 units in 1 building: 89 homes (1, 2 & 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2026, extended by 10 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

94 of its 100 units are booked (94%). Since the December 2025 update, 10 more units have been booked and the possession date has moved from December 2025 to October 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100049675.Check it on MahaRERA (P52100049675)All projects in Charholi, Moshi