Valora Towers, Mundhwa

Lapsed

by Abisky Ritkriti Projects Keshavnagar LLP. Mundhwa, Pune 411036. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
May 2022 – Dec 2023varies by phase2 of 2 phases have an extended possession date. What does Lapsed mean?
Concrete structure (RCC)
56%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
166 of 18988% booked
Price per sq ft
₹6,4002025 salesSee what buyers paid

Project facts

1 BHK2
2 BHK229
Total units231
Buildings2
Land0.3 acres
Phases2
MahaRERA complaints (filed by or against the builder)44

Since Dec 2025: booked 149 → 166

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 780 sq ft₹49 – 50 lakh2025 sales

Price per sq ft, year by year

2025₹6,400 per sq ft

Registered sales across all 2 phases.

Compared with the typical Mundhwa rate in 2025: about 50% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Valora Towers-B
Mid-construction Lapsed
P5210000177612695%75%
Valora Towers-A
Mid-construction Lapsed
P5210002093810510%69%
Show updates by phase

Valora Towers-B (P52100001776)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%94
100%95%0%80
100%0%0%46

"—" means MahaRERA shows no figure for that update.

Valora Towers-A (P52100020938)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%72
100%10%0%69
100%10%0%31
100%10%0%37

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Valora Towers is a project by Abisky Ritkriti Projects Keshavnagar LLP in Mundhwa, Pune 411036, registered with MahaRERA as 2 phases (P52100001776, P52100020938). The first phase was launched in July 2017. Together the phases have 231 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 2 phases are lapsed on MahaRERA.

The phases' registered possession dates run from May 2022 to December 2023; 2 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 56% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

166 of the 189 units reported for sale are booked (88%). In 2025 registered sales, 80% of flats here sold at ₹6,400 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 50% lower than the typical Mundhwa rate in 2025. Most buyers paid ₹49–50 lakh for 2 BHK flats of about 780 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100001776 and P52100020938.Open MahaRERA and search P52100001776All projects in Mundhwa, Keshavnagar