Leisure Town, Hadapsar

by Sai Proviso Homes. Hadapsar, Pune 411028. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 20272 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
95%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
576 of 70182% booked
Price per sq ft
₹10,1002025 salesup 4% on 2024See what buyers paid

Project facts

1 BHK227
2 BHK386
3 BHK88
Total units701
Buildings7
Land5.1 acres
Phases2
MahaRERA complaints (filed by or against the builder)60

Since Dec 2025: booked 577 → 576

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 460 sq ft₹43 – 48 lakh2025 sales
2 BHKabout 740 sq ft₹49 – 67 lakh2023 sales

Price per sq ft, year by year

2023₹9,400 per sq ft
2024up 3% on 2023₹9,700 per sq ft
2025up 4% on 2024₹10,100 per sq ft

Registered sales across all 2 phases.

Compared with the typical Hadapsar rate in 2025: about 15% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Leisure Town Phase 1
Completed
P52100002395560100%93%
Leisure Town Phase 2
Mid-construction
P5210002662114175%39%
Show updates by phase

Leisure Town Phase 1 (P52100002395)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%67%521
100%99%67%521
100%83%67%521

"—" means MahaRERA shows no figure for that update.

Leisure Town Phase 2 (P52100026621)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%55
100%38%0%56
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Leisure Town is a project by Sai Proviso Homes in Hadapsar, Pune 411028, registered with MahaRERA as 2 phases (P52100002395, P52100026621). The first phase was launched in July 2017. Together the phases have 701 units in 7 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is December 2027; 2 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 95% complete and final finishes 54% complete. 1 of the 2 phases have their structure complete.

576 of the 701 units reported for sale are booked (82%). In 2025 registered sales, 80% of flats here sold at ₹10,100 per sq ft or less (up 4% on 2024), counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Hadapsar rate in 2025. Most buyers paid ₹43–48 lakh for 1 RK / 1 BHK flats of about 460 sq ft (2025 sales); ₹49–67 lakh for 2 BHK flats of about 740 sq ft (2023 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100002395 and P52100026621.Open MahaRERA and search P52100002395All projects in Hadapsar, Handewadi