Pankaj Aasmaan, Lohegaon

by Pankaj Developers. Lohegaon, Pune 411047. View on Google Maps

Launched
First of 5 phases
Possession dates (MahaRERA)
Sep 2022 – Dec 2027varies by phase4 of 5 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
85%Mid-construction4 of 5 phases with structure completeWeighted across 5 phases
Units booked
217 of 21899% booked · 1 phase not reported
Price per sq ft
₹5,7002024 salesdown 3% on 2023See what buyers paid

Project facts

1 BHK13
2 BHK256
3 BHK53
Total units322
Buildings13
Land2.4 acres
Phases5
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 219 → 153

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 730 – 840 sq ft₹44 – 45 lakh2023 sales
3 BHKabout 950 sq ft₹45 – 55 lakh2024 sales

Price per sq ft, year by year

2023₹5,900 per sq ft
2024down 3% on 2023₹5,700 per sq ft

Registered sales across all 5 phases.

Compared with the typical Lohegaon rate in 2024: about 30% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Pankaj Aasmaan Phase II
Ready to move Lapsed
P5210000564938100%29%
Pankaj Aasmaan Phase III
Ready to move
P52100016512120100%76%
Pankaj Aasmaan Phase IV
Ready to move
P5210002360764100%100%
Pankaj Aasmaan Phase V
Early stage
P52100023613480%Not reported
Pankaj Aasmaan Phase VI
Nearing possession
P5210002370952100%98%
Show updates by phase

Pankaj Aasmaan Phase II (P52100005649)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%11
100%100%100%77
100%100%100%75

"—" means MahaRERA shows no figure for that update.

Pankaj Aasmaan Phase III (P52100016512)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%91
100%100%95%91
100%100%95%119
100%75%63%73

"—" means MahaRERA shows no figure for that update.

Pankaj Aasmaan Phase IV (P52100023607)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%64
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Pankaj Aasmaan Phase V (P52100023613)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Pankaj Aasmaan Phase VI (P52100023709)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%38%51
50%0%0%51
50%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Pankaj Aasmaan is a project by Pankaj Developers in Lohegaon, Pune 411047, registered with MahaRERA as 5 phases (P52100005649, P52100016512, P52100023607, P52100023613, P52100023709). The first phase was launched in August 2017. Together the phases have 322 units in 13 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 4 are active and 1 is lapsed.

The phases' registered possession dates run from September 2022 to December 2027; 4 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 85% complete and final finishes 75% complete. 4 of the 5 phases have their structure complete.

217 of the 218 units reported for sale are booked (99%); 1 phase has not reported bookings. In 2024 registered sales, 80% of flats here sold at ₹5,700 per sq ft or less (down 3% on 2023), counting balconies and terrace in the size. Buyers here paid a rate about 30% lower than the typical Lohegaon rate in 2024. Most buyers paid ₹44–45 lakh for 2 BHK flats of about 730–840 sq ft (2023 sales); ₹45–55 lakh for 3 BHK flats of about 950 sq ft (2024 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100005649, P52100016512, P52100023607, P52100023613 and P52100023709.Open MahaRERA and search P52100005649All projects in Lohegaon