Skip to main content
← Back

Sai Shawas, Wade Bolhai

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Vilas Tukaram Wadghule. Wade Bolhai, Pune 412207. View on Google Maps

Launched
5 years 4 months originally promised
Possession date (MahaRERA)
10 months ago. No further extension recordedExtended by 3 years (originally December 2022). Why possession dates change
Concrete structure (RCC)
100%Finishing stageAverage across 3 buildings
Units booked
168 of 19885% booked

Project facts

1 BHK95
2 BHK75
3 BHK28
Total units198
Buildings3
Land2 acres
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: complaints 0 → 2

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 5 years 4 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 73%Jun 2024: Final finishes 73%Dec 2024: Final finishes 97%Jun 2025: Final finishes 97%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%168
100%100%97%124
100%100%73%124

"—" means MahaRERA shows no figure for that update.

About this project

Sai Shawas (MahaRERA P52100007646) is a residential project by Vilas Tukaram Wadghule in Wade Bolhai, Pune 412207. It was launched in August 2017. It has 198 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2025, after an extension of 3 years from the original December 2022. That date has passed and no further extension has been recorded. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

168 of its 198 units are booked (85%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100007646.Check it on MahaRERA (P52100007646)All projects in Wagholi