Rajveer Imperia, Pimpri
Finishing stageLapsed
Final finishes 99% · completion not yet filed on MahaRERA
by Waghere Associates. Pimpri, Pune 411018. View on Google Maps
- Launched
- 8 years 4 months promised
- Possession date (MahaRERA)
- 10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stageAverage across 6 buildings
- Units booked
- 256 of 31581% booked
Project facts
| 1 BHK | 8 |
|---|---|
| 2 BHK | 204 |
| 3 BHK | 22 |
| Other units (shops, offices or not given by type) | 81 |
| Total units | 315 |
| Buildings | 6 |
| Land | 4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 252 → 256 · structure 89% → 100% · final finishes 81% → 99%
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 256 | |
| 100% | 89% | 81% | 252 | |
| 100% | 89% | 81% | 307 | |
| 100% | 89% | 81% | 176 |
"—" means MahaRERA shows no figure for that update.
About this project
Rajveer Imperia (MahaRERA P52100009270) is a residential project by Waghere Associates in Pimpri, Pune 411018. It was launched in August 2017. It has 315 units in 6 buildings: 234 homes (1, 2 & 3 BHK) and 81 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction, averaged across its 6 buildings: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
256 of its 315 units are booked (81%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 89% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.